How Long Does a Kitchen Remodel Take? (Irving, TX)

Free Estimate on SiteCalls Answered by a Live Person, 24/7Background-Checked TechniciansA Local Team in Irving
A stone counter, tile backsplash and open shelf after a kitchen remodel
New painted shaker cabinets with an organized deep drawer
A remodeled kitchen with a waterfall island and wood cabinets
A new white vinyl privacy fence with a double gate
A remodeled hall bathroom with patterned floor tile and painted walls
A wood double vanity with two mirrors after a bathroom remodel
A finished backyard cottage with a small covered porch
A new roof with clean valleys and new flashing
Every visit starts with

Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled

We have financing partners for your dream remodel*On approved credit; ask us about your options
Get your free estimate
Explore

Styles & brands we work with

  • Kitchen remodeling
  • Bathroom remodeling
  • Home additions & ADU
  • Roofing
  • Windows & doors
  • Driveway & pavers
  • Fence
Before & after

See the difference

Before - Recent ProjectBeforeAfter - Recent ProjectAfter
Recent Project
Before - Full RestorationBeforeAfter - Full RestorationAfter
Full Restoration
Before - Complete UpgradeBeforeAfter - Complete UpgradeAfter
Complete Upgrade

How Long Does a Kitchen Remodel Take in Irving, TX? The Honest Timeline, Permit Clock and All

A typical mid-scope kitchen remodel in Irving runs 10 to 16 weeks from contract signing to final walkthrough, not the “six to eight weeks” you’ll hear on the phone. Most of the overage isn’t construction labor – it’s the City of Irving building department, which is currently running about 10 to 14 business days on kitchen permit reviews, and that clock doesn’t even start until your drawings are submitted. Week one of your “eight-week remodel” is often week zero, before a single nail moves. If you want a schedule built on named milestones instead of a week count, call Barrett & Sons Construction Irving at (833) 991-4970 for a free, no-pressure estimate.

Irving sits between DFW Airport and Dallas, and its housing stock splits hard. The 1950s-70s ranches in south Irving often sit on pier-and-beam foundations that add real steps to a kitchen schedule, while the 1980s-2000s homes in Las Colinas and Valley Ranch bring their own HOA architectural reviews. Expansive black clay soil underneath both means drainage and foundation questions surface during any remodel that touches the floor. None of that fits a generic timeline. A real one has gates.

Installers leveling a new base cabinet during a kitchen remodel

What does a realistic phase-by-phase kitchen schedule actually look like?

Here’s what we build for a mid-scope Irving kitchen: Kitchen Remodeling scheduled phase by phase, with a written milestone for each step and a sign-off before the next one starts. It’s more pages than a “we’ll be done in eight weeks” text, and it’s the only version that holds up when the permit queue moves or a sewer camera finds what it finds.

  • Design and permit submission – 2 to 3 weeks. Drawings, allowances in writing, and the permit package go to the City of Irving. This phase overlaps with product ordering.
  • Cabinet delivery lead time – 4 to 6 weeks from order. KraftMaid semi-custom cabinets are ordered during the design phase, not after demo, so the lead time runs parallel to permitting. Order after demo and you’ll add five weeks to a kitchen with nothing in it.
  • Demo and rough-in inspections – 1 to 2 weeks. Add time for the City of Irving inspection scheduling window. Rough-in isn’t done until the inspector signs.
  • Installation and finish trades – 2 to 3 weeks. Cabinets, counters (Cambria quartz runs its own fabrication window), tile, appliances, plumbing trim, electrical trim.
  • Punch list – 3 to 5 days. The final walkthrough with a written list. Anything on it gets fixed under the 90-Day Done Right Promise.

Stack those honestly and you’re at 10 to 16 weeks. That’s the schedule we put in writing, with a gate at each milestone – not a hopeful week count scrawled on an estimate.

Why does a south Irving kitchen schedule fork more often than a Las Colinas one?

Because of what’s under the floor. In south Irving’s older pier-and-beam homes, the city’s rough-in inspection routinely triggers a camera inspection of the existing cast-iron drain stack. Original cast iron from the 1950s and 60s is collapsing across those neighborhoods, and if the camera shows a failure, your schedule forks into a sewer replacement track that adds at least 1 to 2 weeks – often more, depending on how much line needs to come out.

The right move is to scope that risk in writing before demo, not after the inspector hands you a red tag. We write the sewer contingency as a named gate in the project schedule: if the camera passes, you move straight to installation; if it fails, you get a written change order with the sewer replacement cost and schedule impact spelled out before anybody swings a hammer. An allowance that isn’t on paper is a surprise waiting for a date.

In Las Colinas and Valley Ranch, the schedule fork is different. Those master-planned communities have strict HOA architectural reviews, and exterior changes touching a kitchen remodel – a new patio door, a vent hood routed through the roof – can sit in committee for a couple weeks. We build that review into the front of the schedule instead of discovering it mid-job.

New architectural shingles with a clean valley

What appliance delays in the DFW market can throw your finish date?

Custom-panel appliances and professional ranges are running 8 to 16 weeks from major DFW distributors right now. That’s longer than most kitchen schedules from demo to punch list, which means a homeowner who orders the range at rough-in gets a finished, beautiful kitchen that sits empty for two months waiting on a refrigerator.

The fix is simple and unglamorous: order appliances before demo begins. Ordered during design, they land right around cabinet install. Ordered at rough-in, they land long after everything else is finished. Same for any specialty sink, custom hood, or imported tile you’re set on. We flag lead-time items on the milestone calendar the day we sign the contract, with the order deadline written on the schedule.

How do North Texas heat and concrete cure time affect the schedule?

They matter more than most contractors admit. Irving’s expansive black clay soil and summer heat above 100°F shorten concrete’s open working time, so any concrete board, mortar bed, or exterior concrete work scheduled in July and August gets poured in the early morning and given the full cure window before the next phase. We write cure time into the milestone calendar rather than pretending it doesn’t exist. The clay also means foundation questions surface during a kitchen remodel that touches the floor – sometimes during demo, sometimes during the rough-in inspection. Both are better caught as a scheduled gate than as a surprise.

Here’s roughly what a mid-scope Irving kitchen remodel runs, so you can budget the schedule alongside the cost:

Item Irving range
Mid-scope kitchen remodel (full) $14,000 – $45,000
Small kitchen remodel $9,000 – $20,000
Cabinet installation $4,000 – $13,000
Countertop installation $2,000 – $6,500
Kitchen island installation $3,000 – $10,000
Backsplash installation $800 – $2,500

A smaller scope compresses the labor timeline but not the permit or cabinet clock – a small kitchen remodel still needs City of Irving review and still waits 4 to 6 weeks on KraftMaid. So don’t assume a $9,000 job is done in four weeks. The schedule floor is set by the permit queue and delivery lead times, not the size of the job.

What does a written project schedule from Barrett & Sons look like?

Each milestone is a named decision gate with a sign-off from you before the next phase begins. You always know where the job sits and what’s coming – not just a contractor telling you he’ll be done in eight weeks with no more detail than that. Our technicians bring up to 28 years of experience, and every eligible job gets permits pulled and inspections signed, because the last contractor most folks used told them permits were optional.

Two things we don’t do: surprise invoices at the end, and vague finish dates. Every scope change, allowance adjustment, and price change arrives as a written change order before work proceeds. And every completed job is backed by the written 90-Day Done Right Promise – if something’s not right, one call brings the crew back.

You can see the broader service on our Kitchen Remodeling in Irving page. Curious how these timelines hold up? Ask a neighbor on your street who’s had a kitchen done in the last couple years – or look up the license number, because it’s published and verifiable.

FAQs

Getting started with Barrett in Irving

Every project starts with a conversation and a written price. Here is how to take the first step.

A project lead walking the house with the homeowner during a free estimate

Free on-site estimate

A project lead walks the job with you, measures it and hands you a written, line-item price. No obligation.

Book an estimate
A crew arriving at a home with materials and tools

Your Irving team

A local vetted partner works across Irving and the towns around it, to the same written standard as every Barrett job.

Areas we serve
A worker laying floor protection before work starts

Read our written promise

What we promise on every job, written down, with the terms spelled out before any work starts.

Our promise
Need Construction help in Irving? Licensed & insured · free written estimates
Call (833) 991-4970
Local Service Coverage

Request a Free Estimate in Irving

Tell us what you need - Barrett & Sons Construction Irving responds fast. No obligation.

By submitting this form you agree to our Privacy Policy and consent to be contacted by phone, email or SMS about your request, including by local professionals who may handle it.

Prefer to text? Send a Text
Call Now - 24/7 Dispatch